Exelon separates data center power demand into high-probability and pipeline groups
Exelon's October 30 earnings materials split projected data center demand into about 11 GW of high-probability load and roughly 23 GW in a future pipeline. The company defines the higher-confidence group as projects in advanced design or backed by FERC-approved transmission security agreements, with about 45% of that group holding such agreements. The figures appear on slide 15 of the third-quarter presentation. The disclosure concerns projected demand and does not confirm that corresponding facilities have been energized. The article's author argues that infrastructure teams should track each site's specific power milestone separately from regional demand forecasts.