Builder ordered to refund Rs 1.96 crore with 12% interest to investor family
A family invested nearly Rs 2 crore to set up a cloth retail business in Zirakpur. The project faced major delays, and the assured returns promised under the agreement with the developer were never paid. When construction stalled, the family sought a refund, but the developer refused. The State Consumer Disputes Redressal Commission ruled in the family's favour and ordered the builder to repay the amount with 12% interest.